What Are Groundworks? The First Stage of Any New Build

In short

Groundworks are the first stage of construction, carried out before anything is built above ground. They include site clearance, excavation, foundations, drainage, ducts for incoming services and the ground floor slab. They give the building a stable, level and properly drained base.

Groundworks are everything that happens in and below the ground before walls start to rise. On a new build or a large extension they are often the least visible part of the project and one of the most important, because every mistake made in the ground is expensive to put right once the building is on top of it. In London, where sites are tight, soils are often shrinkable clay and old drains run everywhere, careful groundworks set the tone for the whole job.

What groundworks include

  • Site setup and clearance: hoarding, welfare, demolition of old structures, removing vegetation and topsoil.
  • Setting out: marking the exact position and levels of the building from the approved drawings.
  • Excavation: digging foundation trenches or reducing levels, and removing spoil from site.
  • Foundations: concrete strip, trench fill, raft or piled foundations, as designed by the structural engineer. Our guide to strip and raft foundations explains the main options.
  • Drainage: new foul and surface water drains, connections to the sewer, and any soakaways or attenuation tanks.
  • Service ducts: routes for water, gas, electricity and data to come into the building.
  • Ground floor slab: sub base, membrane, insulation and concrete slab or a suspended floor.

Why groundworks matter so much in London

Much of London sits on clay that swells when wet and shrinks when dry. Trees nearby make that movement worse, so foundations often need to go deeper than people expect. Sites can also hide old cellars, wells, made ground and redundant drains. Working near neighbours means thinking about access, noise, spoil removal and the Party Wall etc. Act 1996 where excavation is close to an adjoining building.

Inspections and approvals

Building control inspects foundation excavations before concrete is poured, and drainage is usually inspected or tested before it is backfilled. Connections to the public sewer, or building over or near one, may need consent from the water company. These checks are part of building regulations approval, and skipping them can cause problems at sign off.

What affects cost and programme

Ground conditions are the biggest unknown, which is why a soil investigation before pricing is worth doing on a new build. Depth of foundations, the amount of spoil to remove, access for machinery, drainage routes and the weather all affect cost and time. A clear allowance for the unknowns, such as a provisional sum, is better than a surprise later.

How we handle groundworks on London’s Prestige projects

We plan groundworks around the structural engineer’s design and any soil investigation, arrange building control inspections at each stage, and keep neighbours informed about access and deliveries. Your project manager records levels, depths and drainage runs with photos before they are covered, so you have a full record of what sits beneath your building. See the groundworks behind our Meadway Close wraparound extension, learn about our new build service, and book a site visit to talk through your plot.

Common questions

How long do groundworks take on a new build?

It depends on the size of the building, ground conditions, foundation type and weather. For a single house, groundworks often take several weeks. Poor ground, deep foundations or complex drainage add time, which is why a soil investigation before pricing is so useful.

Do I need a soil investigation before groundworks?

For a new build it is strongly recommended and often required by the structural engineer or warranty provider. It tells the engineer what the ground can carry and how deep foundations should go, which reduces the risk of costly changes once digging starts.

Who inspects groundworks?

Building control inspects foundation excavations before concrete is poured and checks drainage before it is covered. A structural warranty provider may also inspect. The structural engineer may visit to confirm the ground matches the design assumptions.