Full Planning Permission Explained: When You Need It
In short
Full planning permission is formal approval from your local council for building work or a change of use that falls outside permitted development. You submit drawings and supporting documents, the council consults neighbours and assesses the proposal, and a decision is usually due within eight weeks for householder and minor applications.
Full planning permission is needed whenever your project goes beyond what permitted development allows. In London, that covers a large share of ambitious home projects: mansard roofs, most double storey extensions, side return and wraparound extensions on many streets, work to flats, and almost anything in a conservation area. Getting it right first time is one of the biggest factors in how quickly your project can start.
When you are likely to need it
- Extensions larger than permitted development limits, or of a type not covered
- Mansard roofs and front facing roof alterations
- Any extension or external alteration to a flat or maisonette
- Work in conservation areas or areas covered by an Article 4 direction
- New buildings, new dwellings and splitting a house into flats
- Most changes of use
Projects to houses are usually submitted as a householder application; flats, new dwellings and commercial schemes use a full application. Listed buildings also need listed building consent.
How the process works
- Pre application advice (optional): many London councils offer paid advice before you apply. Useful for sensitive sites.
- Submission: drawings of the existing and proposed building, a site location plan, the application form and fee, plus any supporting documents such as a design and access or heritage statement.
- Validation: the council checks the application is complete before the clock starts.
- Consultation: neighbours are notified and can comment, usually for 21 days.
- Assessment: a planning officer visits and weighs the proposal against local and national policy.
- Decision: the target is eight weeks for householder and minor applications, thirteen for major schemes, although some councils run late.
After the decision
Approvals come with conditions, often on materials, and some must be discharged before work starts. Permission usually lasts three years. If refused, you can amend and resubmit, or appeal. Householder appeals generally have to be lodged within 12 weeks of the decision.
How to improve your chances
- Read your council’s design guidance for extensions, lofts and conservation areas.
- Look for approved precedents on your street.
- Present clear, accurate drawings that answer the officer’s likely concerns.
- Talk to neighbours before they receive the consultation letter.
How we handle planning on London’s Prestige projects
We work with experienced designers to prepare drawings that reflect how London councils assess applications, track the application through to decision, and build discharge of conditions and lead in times into your programme so the build can start as soon as approval is in place. Our Corbyn Street loft and extension shows the kind of project we take from approval to handover. Read our guide on planning permission for London extensions, explore our extension service, and book a site visit to talk through what your project will need.
Common questions
How long does full planning permission take in London?
The target is eight weeks from validation for householder and minor applications. Allow extra time for preparing drawings, validation and any requests for amendments.
How long does planning permission last?
Usually three years from the decision date. Work must start within that time, and any pre commencement conditions must be discharged first.
What is the difference between householder and full planning applications?
A householder application covers extensions and alterations to a single house. Flats, new dwellings, changes of use and commercial work use a full planning application.